This document provides information about construction dewatering and permanent groundwater control techniques. It discusses the differences between construction dewatering, which involves temporarily lowering the groundwater table during construction, and permanent groundwater control, which blocks long-term groundwater flow. Various dewatering techniques are described, including sump pumping, shallow wells, well points, and deep wells. Methods for permanent groundwater control include ground freezing, slurry trench walls, steel sheet piling, grouted barriers, thin grouted membranes, contiguous piling, diaphragm walls, and grouting. The document also provides examples of applying these techniques and outlines their advantages and disadvantages.
Caissons are watertight structures used as foundations when construction needs to be done under water or in locations with a high water table. They are constructed out of materials like wood, steel, or reinforced concrete. There are different types of caissons including open caissons, box caissons, and pneumatic caissons. Caissons are sunk into position using methods like dredging or compressed air in a pneumatic caisson. Proper construction involves building curbs, plugs, and reinforcement to withstand loads and facilitate controlled sinking. Caissons allow foundations to be constructed in deep underwater locations for structures like bridges, piers, and buildings.
The document discusses different types of well foundations used in construction. It describes the key components of well foundations including the cutting edge, steining, bottom plug, top plug, and well cap. It explains the process of sinking well foundations, which involves excavating material inside the well curb to allow the well to sink vertically into the ground. Precautions like maintaining verticality and limiting tilt and shift are important during well sinking.
This document provides an overview of hydraulic structures and classifications of dams. It discusses:
1) Different types of dams classified by function (storage, detention, diversion), design (overflow, non-overflow), structure (gravity, arch, buttress, embankment), and materials (rigid, non-rigid).
2) Characteristics and components of earth dams including homogeneous, zoned, and diaphragm types.
3) Characteristics of rock fill dams and combined earth and rock fill dams.
4) Advantages and disadvantages of gravity dams, arch dams, and buttress dams constructed of concrete.
1. Dams are constructed across rivers to store flowing water for uses like hydropower, irrigation, water supply, flood control, and navigation.
2. The key forces acting on a gravity dam include its self-weight, which provides stability, and water pressure from the reservoir, which acts to overturn the dam. Uplift, earthquake loads, silt pressure, and ice pressure are other important forces that must be estimated based on assumptions and available data.
3. The weight of the dam per unit length is calculated based on the cross-sectional area and unit weight of the concrete or masonry used. The total weight acts at the centroid of the cross-section and is the main stabil
The document discusses various methods of soil exploration including borings, test pits, and geophysical methods. It describes the objectives of soil exploration as determining the suitable foundation type, bearing capacity, and other factors. The key methods discussed are displacement boring, wash boring, auger boring, rotary drilling, percussion drilling, and continuous sampling boring. Each method is explained along with its suitable soil conditions, advantages, and limitations.
Factors to consider in foundation designMushtaq Zaib
Factors to consider in foundation design include: footing depth and spacing, location of spread footings, soil pressures, erosion risks for structures near water, corrosion protection, water table fluctuations, and properties of soil types like sand, silt, loess, clays, and expansive soils. Designs must account for frost depth, moisture changes, unsuitable subsurface materials, adjacent existing structures, net versus gross pressures, predicted scour depths, corrosion risks, drainage, and consolidation settlements.
This document discusses different types of well foundations used in construction. It describes three main types: open caissons, which have open tops and bottoms; pneumatic caissons, which use air pressure; and box caissons, which are closed at the bottom. It provides details on each type, including advantages and disadvantages. Open caissons can be built to greater depths but inspection of the bottom is not possible. Pneumatic caissons allow work under water but require complex machinery. Box caissons have a lower construction cost but the foundation base cannot be inspected.
1. Dams are constructed across rivers to store flowing water and come in various types like earth, rockfill, gravity, steel, timber and arch dams. The selection of dam type depends on site conditions like topography, geology and availability of construction materials.
2. Gravity dams derive their strength from their weight and weight of water pressure pushing them into the ground. They are made of concrete or masonry and work by balancing the water pressure on upstream side with weight and pressure on downstream side.
3. Factors considered in gravity dam design include water pressure, seismic forces, uplift pressure, weight of dam, and ensuring stability against sliding, overturning and cracking. Galleries are provided for drainage,
This document discusses the key forces acting on a gravity dam, including its weight, water pressure, uplift pressure, silt pressure, wave pressure, and earthquake forces. It defines key terms like structural height, maximum base width, and hydraulic height. It also provides details on how to calculate or estimate the various forces, for example explaining that water pressure acts normal to the face of the dam and can be calculated based on horizontal and vertical components. Uplift pressure is defined as the upward pressure of water seeping through the dam or its foundation. Earthquake forces cause random vibrations that impart accelerations to the dam's foundation.
This presentation explains different methods of dewatering of ground water during construction works and suggests the suitability of particular method in particular context.
Spillway crest gates are adjustable gates used to control water flow in reservoir and river systems. They act as barriers to store additional water, allowing the height of dams to be increased and requiring more land acquisition. The main types of spillway gates are dripping shutters, stop logs, radial/tainter gates, drum gates, and vertical lift/rectangle gates. Vertical lift gates are rectangular gates that spin horizontally between grooved piers and can be raised or lowered by a hoisting mechanism to control water flow.
This document discusses various types of canal regulation works including canal falls, escapes, regulators, and outlets. It describes the necessity and types of canal falls, which are constructed when the natural ground slope is steeper than the designed canal bed slope. The types of falls discussed include ogee falls, stepped falls, vertical falls, rapid falls, straight glacis falls, trapezoidal notch falls, well or cylinder notch falls, Montague type falls, and Inglis or baffle falls. The document also discusses canal escapes, head regulators, cross regulators, silt control devices, and canal outlets/modules. In particular, it explains the functions and construction of head regulators and cross regulators.
Caissons are large, box-like foundations that are sunk into the ground or water to transfer structural loads to deeper, stronger soil layers. There are three main types: box caissons, which are enclosed boxes opened at the top; open or well caissons, which are open at the top and bottom; and pneumatic caissons, which use compressed air to allow construction under water. Caissons are made of materials like concrete, steel, or timber and are used as foundations for bridges, dams, and other structures. Workers inside pneumatic caissons can experience health issues if not properly managed during decompression.
Diversion headworks are structures constructed at the head of a canal to divert river water into the canal. They include components like weirs, barrages, canal head regulators, divide walls, fish ladders, and guide banks. The objectives are to raise water levels, control silt entry, regulate water flow, and allow fish passage. Proper site selection and design are needed to prevent failures from subsurface water flow, uplift pressure, hydraulic jumps, or scouring during floods. Remedies include increasing seepage lengths, adding sheet piles, and using thicker impervious floors.
Dewatering is the process of removing water from construction sites to allow excavation work to be done safely and efficiently below the water table. There are several reasons why dewatering is needed, including providing a dry work area, improving stability, and increasing safety. Common dewatering techniques include sump pumping, well points, deep wells, and trenches. Each method has advantages and disadvantages depending on the site conditions and depth of water lowering required. Proper planning and design of a dewatering system is important to effectively control groundwater and allow construction work to progress smoothly.
Proper selection of a dam site requires consideration of several criteria:
1) The site should have a gentle slope and receive adequate rainfall to fill the reservoir.
2) The site should be away from populated and agricultural areas to minimize displacement of people and property submergence.
3) The soil and geology of the site must be suitable to safely support the dam structure and prevent water leakage.
This document discusses different types of cofferdams used in construction projects. It describes earth-fill, rock-fill, single-walled, double-walled, crib, cellular, concrete, suspended, and sandbag dike cofferdams. For each type, it provides details on suitable applications based on water depth and flow, and construction methods. The overall purpose of a cofferdam is to temporarily enclose an area of water to allow work to proceed in dry conditions.
This document provides information on coffer dams and caissons. It discusses different types of coffer dams such as braced, earth-type, double-walled sheet pile, and cellular coffer dams. It also discusses environmentally friendly portable coffer dams. A case study on coffer dam construction for the Taunsa Barrage Rehabilitation Project in Pakistan is presented. Caissons are described as prefabricated foundations sunk into the ground to form foundations. Different types of caissons including box, open, pneumatic, and monolith caissons are discussed. Construction methods and examples of caisson usage are also summarized.
This document discusses different types of foundations, including shallow and deep foundations. Shallow foundations include spread footings, combined footings, strap footings, and raft/mat foundations. Deep foundations include pile foundations, pier foundations, and caisson/well foundations. It also discusses considerations for foundations on expansive black cotton soil, recommending methods like strip foundations, pier foundations, and under-reamed pile foundations.
Dewatering involves controlling groundwater by pumping, to locally lower groundwater levels in the vicinity of the excavation. The simplest form of dewatering is sump pumping, where groundwater is allowed to enter the excavation where it is then collected in a sump and pumped away by robust solids handling pumps.
This document discusses different grouting methods. It describes permeation grouting where grout is injected to fill voids without disturbing soil grains. Displacement grouting displaces soil grains, including compaction grouting using thick grout to form bulb shapes, and soil fracture grouting using lean grout to form root-like lenses. Jet grouting forms grouted columns by partly replacing and mixing with soil. Permeation grouting is used to form seepage barriers and stabilize tunnels. Displacement-compaction grouting involves high pressure injection of a soil-cement grout mixture to form 0.5-1m bulbous intrusions.
Joints are easy to maintain and are less detrimental than uncontrolled or uneven cracks. Concrete expands & shrinks with variations in moisture and temp. The overall affinity is to shrink and this can cause cracking at an early age. Uneven cracks are unpleasant and difficult to maintain but usually do not affect the integrity of concrete.
pipe expansion joint us bellows us bellows catalogue rubber expansion joint metal expansion joints driveway expansion joint filler flexi craft expansion joints building expansion joint systems
construction joint vs expansion joint construction joint vs control joint sidewalk control joint spacing concrete wall control joints expansion joint concrete construction joint concrete concrete joints control joint
monolithic isolation joints isolation joint material isolation joint vs expansion joint isolation joint neo prene insulating joints pipeline isolation joint vs control joint isolation joints in concrete concrete slab isolation joint
construction joint vs expansion joint construction joint vs control joints idewalk control joint spacing concrete wall control joints expansion joint concrete construction joint concrete concrete joints control joint
concrete joint filler
concrete joint filler strips
control joint vs construction joint concrete
concrete control joint filler
concrete slab control joint detail
types of concrete expansion joints
construction joint concrete
control joints in concrete
Pile foundations are required for large structures. Different pile types can be installed using various equipment, even in layered soils, making safe and economical installation difficult. Dynamic pile load testing methods like low-strain integrity testing and high-strain load testing provide alternatives to static pile load testing by being more economical and efficient while still providing pile capacity and integrity information. Dynamic testing has been used successfully on numerous infrastructure projects to test piles efficiently and help reduce costs and schedule.
This document provides an overview of groundwater control for construction. It defines groundwater control as temporarily dealing with groundwater to allow excavations below the water table. The main approaches to groundwater control are exclusion, using physical barriers like cut-off walls, and pumping using well arrays. Good design requires understanding site conditions through investigation to develop an appropriate conceptual model and select analysis methods. Both empirical and analytical approaches are used, with numerical modeling for more complex sites. Observational methods also allow adapting designs based on monitoring.
Coffer dams are temporary structures built to retain water and soil in order to create a dry work area for construction projects. There are several types of coffer dams suited to different conditions, including earth-filled, sheet pile, and cellular designs. Key considerations in selecting a coffer dam include water depth, area size, soil/river bed conditions, and potential for erosion or flooding. Proper design is needed to withstand hydrostatic pressures and ensure structural integrity until the permanent structure is complete.
1) The document discusses soil bearing capacity, which refers to the capacity of soil to support loads applied to the ground without failing.
2) Important factors in soil bearing capacity include the stability of foundations, which depends on the bearing capacity of soil beneath and the settlement of soil.
3) The document outlines several key terminologies used in soil bearing capacity such as ultimate bearing capacity, net ultimate bearing capacity, net safe bearing capacity, and more.
4) Several methods to increase the bearing capacity of black cotton soil are described, including increasing foundation depth, chemical treatment, grouting, compaction, drainage, and confining the soil.
Ground freezing involves inserting freeze pipes vertically into the soil and circulating chilled brine to slowly form a solid ice wall. It has several purposes, including controlling groundwater, providing earth support, and stabilizing soil for tunnel excavation. The process involves lowering the soil temperature around the freeze pipes until the water in the pores freezes and binds the soil particles. This creates a strong, impermeable frozen barrier with advantages like minimal risk to surrounding structures and the ability to freeze at unlimited depths. Common applications include supporting circular excavations and shaft sinking.
This document provides information about constructing a diaphragm wall for basement excavation using the diaphragm wall method. It discusses what a diaphragm wall is, its applications, and the steps involved in constructing one including excavating a pre-trench, installing guide walls and reinforcement cages, concreting using tremie tubes, and joining wall panels with water stops. It also addresses selecting suitable temporary excavation support systems, advantages of diaphragm walls, excavator machines used, and providing additional wall support with ground anchors.
1. Dams are constructed across rivers to store flowing water and come in various types like earth, rockfill, gravity, steel, timber and arch dams. The selection of dam type depends on site conditions like topography, geology and availability of construction materials.
2. Gravity dams derive their strength from their weight and weight of water pressure pushing them into the ground. They are made of concrete or masonry and work by balancing the water pressure on upstream side with weight and pressure on downstream side.
3. Factors considered in gravity dam design include water pressure, seismic forces, uplift pressure, weight of dam, and ensuring stability against sliding, overturning and cracking. Galleries are provided for drainage,
This document discusses the key forces acting on a gravity dam, including its weight, water pressure, uplift pressure, silt pressure, wave pressure, and earthquake forces. It defines key terms like structural height, maximum base width, and hydraulic height. It also provides details on how to calculate or estimate the various forces, for example explaining that water pressure acts normal to the face of the dam and can be calculated based on horizontal and vertical components. Uplift pressure is defined as the upward pressure of water seeping through the dam or its foundation. Earthquake forces cause random vibrations that impart accelerations to the dam's foundation.
This presentation explains different methods of dewatering of ground water during construction works and suggests the suitability of particular method in particular context.
Spillway crest gates are adjustable gates used to control water flow in reservoir and river systems. They act as barriers to store additional water, allowing the height of dams to be increased and requiring more land acquisition. The main types of spillway gates are dripping shutters, stop logs, radial/tainter gates, drum gates, and vertical lift/rectangle gates. Vertical lift gates are rectangular gates that spin horizontally between grooved piers and can be raised or lowered by a hoisting mechanism to control water flow.
This document discusses various types of canal regulation works including canal falls, escapes, regulators, and outlets. It describes the necessity and types of canal falls, which are constructed when the natural ground slope is steeper than the designed canal bed slope. The types of falls discussed include ogee falls, stepped falls, vertical falls, rapid falls, straight glacis falls, trapezoidal notch falls, well or cylinder notch falls, Montague type falls, and Inglis or baffle falls. The document also discusses canal escapes, head regulators, cross regulators, silt control devices, and canal outlets/modules. In particular, it explains the functions and construction of head regulators and cross regulators.
Caissons are large, box-like foundations that are sunk into the ground or water to transfer structural loads to deeper, stronger soil layers. There are three main types: box caissons, which are enclosed boxes opened at the top; open or well caissons, which are open at the top and bottom; and pneumatic caissons, which use compressed air to allow construction under water. Caissons are made of materials like concrete, steel, or timber and are used as foundations for bridges, dams, and other structures. Workers inside pneumatic caissons can experience health issues if not properly managed during decompression.
Diversion headworks are structures constructed at the head of a canal to divert river water into the canal. They include components like weirs, barrages, canal head regulators, divide walls, fish ladders, and guide banks. The objectives are to raise water levels, control silt entry, regulate water flow, and allow fish passage. Proper site selection and design are needed to prevent failures from subsurface water flow, uplift pressure, hydraulic jumps, or scouring during floods. Remedies include increasing seepage lengths, adding sheet piles, and using thicker impervious floors.
Dewatering is the process of removing water from construction sites to allow excavation work to be done safely and efficiently below the water table. There are several reasons why dewatering is needed, including providing a dry work area, improving stability, and increasing safety. Common dewatering techniques include sump pumping, well points, deep wells, and trenches. Each method has advantages and disadvantages depending on the site conditions and depth of water lowering required. Proper planning and design of a dewatering system is important to effectively control groundwater and allow construction work to progress smoothly.
Proper selection of a dam site requires consideration of several criteria:
1) The site should have a gentle slope and receive adequate rainfall to fill the reservoir.
2) The site should be away from populated and agricultural areas to minimize displacement of people and property submergence.
3) The soil and geology of the site must be suitable to safely support the dam structure and prevent water leakage.
This document discusses different types of cofferdams used in construction projects. It describes earth-fill, rock-fill, single-walled, double-walled, crib, cellular, concrete, suspended, and sandbag dike cofferdams. For each type, it provides details on suitable applications based on water depth and flow, and construction methods. The overall purpose of a cofferdam is to temporarily enclose an area of water to allow work to proceed in dry conditions.
This document provides information on coffer dams and caissons. It discusses different types of coffer dams such as braced, earth-type, double-walled sheet pile, and cellular coffer dams. It also discusses environmentally friendly portable coffer dams. A case study on coffer dam construction for the Taunsa Barrage Rehabilitation Project in Pakistan is presented. Caissons are described as prefabricated foundations sunk into the ground to form foundations. Different types of caissons including box, open, pneumatic, and monolith caissons are discussed. Construction methods and examples of caisson usage are also summarized.
This document discusses different types of foundations, including shallow and deep foundations. Shallow foundations include spread footings, combined footings, strap footings, and raft/mat foundations. Deep foundations include pile foundations, pier foundations, and caisson/well foundations. It also discusses considerations for foundations on expansive black cotton soil, recommending methods like strip foundations, pier foundations, and under-reamed pile foundations.
Dewatering involves controlling groundwater by pumping, to locally lower groundwater levels in the vicinity of the excavation. The simplest form of dewatering is sump pumping, where groundwater is allowed to enter the excavation where it is then collected in a sump and pumped away by robust solids handling pumps.
This document discusses different grouting methods. It describes permeation grouting where grout is injected to fill voids without disturbing soil grains. Displacement grouting displaces soil grains, including compaction grouting using thick grout to form bulb shapes, and soil fracture grouting using lean grout to form root-like lenses. Jet grouting forms grouted columns by partly replacing and mixing with soil. Permeation grouting is used to form seepage barriers and stabilize tunnels. Displacement-compaction grouting involves high pressure injection of a soil-cement grout mixture to form 0.5-1m bulbous intrusions.
Joints are easy to maintain and are less detrimental than uncontrolled or uneven cracks. Concrete expands & shrinks with variations in moisture and temp. The overall affinity is to shrink and this can cause cracking at an early age. Uneven cracks are unpleasant and difficult to maintain but usually do not affect the integrity of concrete.
pipe expansion joint us bellows us bellows catalogue rubber expansion joint metal expansion joints driveway expansion joint filler flexi craft expansion joints building expansion joint systems
construction joint vs expansion joint construction joint vs control joint sidewalk control joint spacing concrete wall control joints expansion joint concrete construction joint concrete concrete joints control joint
monolithic isolation joints isolation joint material isolation joint vs expansion joint isolation joint neo prene insulating joints pipeline isolation joint vs control joint isolation joints in concrete concrete slab isolation joint
construction joint vs expansion joint construction joint vs control joints idewalk control joint spacing concrete wall control joints expansion joint concrete construction joint concrete concrete joints control joint
concrete joint filler
concrete joint filler strips
control joint vs construction joint concrete
concrete control joint filler
concrete slab control joint detail
types of concrete expansion joints
construction joint concrete
control joints in concrete
Pile foundations are required for large structures. Different pile types can be installed using various equipment, even in layered soils, making safe and economical installation difficult. Dynamic pile load testing methods like low-strain integrity testing and high-strain load testing provide alternatives to static pile load testing by being more economical and efficient while still providing pile capacity and integrity information. Dynamic testing has been used successfully on numerous infrastructure projects to test piles efficiently and help reduce costs and schedule.
This document provides an overview of groundwater control for construction. It defines groundwater control as temporarily dealing with groundwater to allow excavations below the water table. The main approaches to groundwater control are exclusion, using physical barriers like cut-off walls, and pumping using well arrays. Good design requires understanding site conditions through investigation to develop an appropriate conceptual model and select analysis methods. Both empirical and analytical approaches are used, with numerical modeling for more complex sites. Observational methods also allow adapting designs based on monitoring.
Coffer dams are temporary structures built to retain water and soil in order to create a dry work area for construction projects. There are several types of coffer dams suited to different conditions, including earth-filled, sheet pile, and cellular designs. Key considerations in selecting a coffer dam include water depth, area size, soil/river bed conditions, and potential for erosion or flooding. Proper design is needed to withstand hydrostatic pressures and ensure structural integrity until the permanent structure is complete.
1) The document discusses soil bearing capacity, which refers to the capacity of soil to support loads applied to the ground without failing.
2) Important factors in soil bearing capacity include the stability of foundations, which depends on the bearing capacity of soil beneath and the settlement of soil.
3) The document outlines several key terminologies used in soil bearing capacity such as ultimate bearing capacity, net ultimate bearing capacity, net safe bearing capacity, and more.
4) Several methods to increase the bearing capacity of black cotton soil are described, including increasing foundation depth, chemical treatment, grouting, compaction, drainage, and confining the soil.
Ground freezing involves inserting freeze pipes vertically into the soil and circulating chilled brine to slowly form a solid ice wall. It has several purposes, including controlling groundwater, providing earth support, and stabilizing soil for tunnel excavation. The process involves lowering the soil temperature around the freeze pipes until the water in the pores freezes and binds the soil particles. This creates a strong, impermeable frozen barrier with advantages like minimal risk to surrounding structures and the ability to freeze at unlimited depths. Common applications include supporting circular excavations and shaft sinking.
This document provides information about constructing a diaphragm wall for basement excavation using the diaphragm wall method. It discusses what a diaphragm wall is, its applications, and the steps involved in constructing one including excavating a pre-trench, installing guide walls and reinforcement cages, concreting using tremie tubes, and joining wall panels with water stops. It also addresses selecting suitable temporary excavation support systems, advantages of diaphragm walls, excavator machines used, and providing additional wall support with ground anchors.
Construction dewatering techniques are used to control subsurface water levels during construction projects. Common techniques include sumps, wellpoints, and deep wells. Sumps are useful for shallow dewatering in tight soils. Wellpoints are small-diameter, shallow wells that can effectively dewater coarse soils and are often used in wellpoint systems connected to header pipes and pumps. Deep wells, which use submersible pumps, can lower water levels deeper than wellpoints and are best suited to permeable soils. Other methods like caissons, ground freezing, and underwater excavation are more complex and costly.
The document provides an overview of construction dewatering techniques. It discusses that construction dewatering involves controlling subsurface and surface water to allow construction in dry conditions. Common dewatering methods include sumps, wells, and wellpoints. Sumps are used for shallow localized dewatering while wells can dewater large areas to great depths. Wellpoints are used in coarse soils and operate under vacuum. Other advanced techniques like freezing and deep wells are also discussed. Proper dewatering design requires understanding soil properties, hydrology, and construction needs. Dewatering analysis and testing is required to select the appropriate technique.
Underwater construction involves building structures where foundations or parts will lie underwater. It presents difficulties due to depth and water conditions. Common underwater construction activities include bridges, dams, utilities, and industrial projects. Construction techniques include both wet construction using divers and dry construction using caissons and cofferdams to create a dry work environment. Caissons are permanent watertight structures sunk into place while cofferdams are temporary structures that can be pumped out. Concrete is often placed underwater using a tremie pipe method to displace water and prevent washout of material.
Dewatering is the process of removing water from construction sites to allow for excavation and construction in dry conditions below the water table. It is done through various techniques like sump pumping, well points, deep wells, and eductor systems. The main purposes of dewatering are to provide a dry excavation area, improve stability, and allow for efficient construction. Proper planning and techniques are needed to safely lower the water table and discharge water without causing erosion or other issues.
Pervious concrete (also called porous concrete, permeable concrete, no fines concrete and porous pavement) is a special type of concrete with a high porosity used for concrete flatwork applications that allows water from precipitation and other sources to pass directly through, thereby reducing the runoff from a site and allowing groundwater recharge.
A pervious concrete street
Pervious concrete is made using large aggregates with little to no fine aggregates. The concrete paste then coats the aggregates and allows water to pass through the concrete slab. Pervious concrete is traditionally used in parking areas, areas with light traffic, residential streets, pedestrian walkways, and greenhouses.[1][2] It is an important application for sustainable construction and is one of many low impact development techniques used by builders to protect water quality.
Purpose, Need, Importance, Methods, Causes and types of defects in buildings, Preparation of report on maintenance work, Remedial measures and execution procedure of any one, Types of building maintenance work.
This document discusses cofferdams, which are temporary structures built to remove water from an area and allow construction work under dry conditions. It outlines the requirements, necessity, uses, factors affecting selection, and common types of cofferdams. The types discussed include earthen, rock-filled, sand bag, single wall, double wall, cellular, crib, concrete, and suspended cofferdams. Forces acting on cofferdams and the economical height are also summarized.
Cofferdams are temporary structures used to allow construction in areas that would otherwise be underwater or difficult to work in. They are enclosures that hold back water and soil to create a dry work area. Various types of cofferdams exist, including braced, earth-type, timber crib, double-walled sheet pile, and cellular designs. Proper construction and safety precautions are vital as workers will be exposed to flooding hazards. Leakage is prevented through measures like cement grouting, clay sealing, and tarpaulins.
Excavation and Ground water control1.pptxssusercbae26
This document summarizes different types of excavation including topsoil excavation, rock excavation, muck excavation, and earth excavation. It then discusses various purposes of excavation such as cut and fill excavation, trench excavation, basement excavation, and dredging excavation. Finally, it covers topics related to controlling groundwater and surface water during excavation projects through methods like pumping, cutoff walls, and special techniques.
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
Generally excavation means to loosen and take out materials leaving space above or below ground. Sometimes in civil engineering term earthwork is used which include back-filling with new or original materials to voids, spreading and leveling over an area.
soil retention in construction -Group 7 powerpointLawin Langat
Soil retention is important for plant growth, flood control, and soil functioning. Soil texture and composition determine water retention levels, with sandy soils retaining the least and clay soils retaining the most. Soil can hold considerable amounts of water important for plants and organisms. The maximum water soil can hold is field capacity, while the minimum for plant growth is wilting point. Soil water retention impacts the environment, climate, hydrological cycle, and soil stability. Techniques to retain soil include soil nailing, retaining walls, and different types of excavation methods.
Groundwater can affect engineering structures through several mechanisms:
- It can erode foundations, cause settlement or collapse through volume changes in soil/rock.
- Increase moisture in slopes, reducing stability and increasing landslide risk.
- Impact excavation and construction by flowing towards work sites.
- Reduce bearing capacity and shear strength of soils.
- Cause uplift pressures that can lead to failure of structures.
Proper site investigation is needed to understand subsurface water conditions and mitigate risks.
1. A cofferdam is a temporary structure built around construction sites located underwater to allow workers to perform construction in a dry environment. It is constructed by driving sheet piling into the ground and placing concrete along the bottom to seal it off from water seepage.
2. The main types of cofferdams are braced, earth-type, timber crib, double-walled sheet pile, and cellular. Their construction involves setting up sheet piling, installing bracing frames, placing a concrete seal, and sometimes using bearing piles before dewatering the site.
3. Safety is the top priority in cofferdam construction due to the risk of flooding. Proper design, construction oversight
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
The document discusses site preparation for construction projects, including site investigation, soil investigation, and ground water control. Site investigation involves collecting data about the site, including topography, hydrology, and existing infrastructure. Soil investigation determines site suitability and foundation design through methods like trial pits, augers, and sampling. Ground water control includes temporary dewatering methods like sumps and wellpoints, and permanent barriers like grouted membranes, contiguous piling, and diaphragm walls. Preliminaries works establish temporary facilities and ensure safety/compliance for a construction project.
this presentation describes in details the sinking operation of well foundations in different conditions and situations. the content here is suitable only for basic knowledge and educational purposes.
About:
A helium boosting and decanting system is typically used in various industrial applications, particularly in the production and handling of gases, including helium including leak test of reciprocating cylinder. Here’s a brief overview of its components and functions:
Components
1. Helium Storage Tanks: High-pressure tanks that store helium@ 150 bars.
2. Boosting Pumps: Designed to boost helium pressure up to 150 bar, ensuring efficient flow throughout the system.
3. Decanting Unit: Separates liquid helium from gas, facilitating decanting at pressures of up to 2 bars.
4. Pressure Regulators: Maintain and control the pressure of helium during transport.
5. Control Valves: automatic control valve is provided for the flow and direction of helium through the system.
6. Piping and Fittings: High-quality, corrosion-resistant materials for safe transport.
Functions
• Boosting Pressure: The system boosts helium pressure up to 150 bar for various applications.
• Decanting: Safely decants helium, separating liquid from gas at pressures of up to 2 bar.
• Safety Measures: Equipped with relief valves and emergency shut-off systems to handle high pressures safely.
• Monitoring and Control: Sensors and automated controls monitor pressure and flow rates.
Application:
• Cryogenics: Cooling superconducting magnets in MRI machines and particle accelerators.
• Welding: Used as a shielding gas in welding processes.
• Research: Crucial for various scientific applications, including laboratories and space exploration.
Key Features:
• Helium Storage & Boosting System
• Decanting System
• Pressure Regulation & Monitoring
• Valves & Flow Control
• Filtration & Safety Components
• Structural & Material Specifications
• Automation & Electrical Components
How to Build a Speed Sensor using Arduino?CircuitDigest
Learn how to measure speed using IR sensors in this simple DIY project. This tutorial cover circuit diagram, Sensor calibration and speed calculations and optimized Arduino code for real time speed measurements.
The Golden Gate Bridge a structural marvel inspired by mother nature.pptxAkankshaRawat75
The Golden Gate Bridge is a 6 lane suspension bridge spans the Golden Gate Strait, connecting the city of San Francisco to Marin County, California.
It provides a vital transportation link between the Pacific Ocean and the San Francisco Bay.
TASK-DECOMPOSITION BASED ANOMALY DETECTION OF MASSIVE AND HIGH-VOLATILITY SES...samueljackson3773
The Science Information Network (SINET) is a Japanese academic backbone network for more than 800
universities and research institutions. The characteristic of SINET traffic is that it is enormous and highly
variable
Flex and rigid-flex printed circuit boards (PCBs) can be considered at the basic level some of the most complex PCBs in the industry. With that in mind, it’s incredibly easy to make a mistake, to leave something out, or to create a design that was doomed from the start.
Such design failures can end up leading to an eventual failure by delamination, short circuits, damage to the flex portions, and many other things. The easiest way to circumvent these is to start at the beginning, to design with preventing failure in mind rather than trying to fix existing designs to accommodate for problems.
In this webinar, we cover how to design flex and rigid-flex PCBs with failure prevention in mind to save time, money, and headaches, and what failure can look like.
For more information on our flex and rigid-flex PCB solutions, visit https://www.epectec.com/flex.
كتاب التفاصيل الانشائيه للمنشآت الخرسانيةo774656624
-Zufälligurl zu
peut élus silly mais les mes ishaute quils le aurais sans Les établis qui
des Louis de belle accueillis sell puss père peut olds sects it's allétells peutall asplait suite
Il -12 ) pas cause subit lequel euros le en as détaillé de till
PILONI balo -2
ispeulit Mais anglais appareils guilt gens ils en anglais glory pile le vous près
... still que y pais vida Los play quétejón Less via Leal su abuelos lástimaall) isa las
des audit elleguilt disons s'il souhait sous sirs vous lucius atoutes à pouvait lets pas
il taille glacis Lieu daily qui les jeutaille pas bill Luc jean écumait il taille Lacis just -Zufälligurl zu
peut élus silly mais les mes ishaute quils le aurais sans Les établis qui
des Louis de belle accueillis sell puss père peut olds sects it's allétells peutall asplait suite
Il -12 ) pas cause subit lequel euros le en as détaillé de till
PILONI balo -2
ispeulit Mais anglais appareils guilt gens ils en anglais glory pile le vous près
... still que y pais vida Los play quétejón Less via Leal su abuelos lástimaall) isa las
des audit elleguilt disons s'il souhait sous sirs vous lucius atoutes à pouvait lets pas
il taille glacis Lieu daily qui les jeutaille pas bill Luc jean écumait il taille Lacis just-Zufälligurl zu
peut élus silly mais les mes ishaute quils le aurais sans Les établis qui
des Louis de belle accueillis sell puss père peut olds sects it's allétells peutall asplait suite
Il -12 ) pas cause subit lequel euros le en as détaillé de till
PILONI balo -2
ispeulit Mais anglais appareils guilt gens ils en anglais glory pile le vous près
... still que y pais vida Los play quétejón Less via Leal su abuelos lástimaall) isa las
des audit elleguilt disons s'il souhait sous sirs vous lucius atoutes à pouvait lets pas
il taille glacis Lieu daily qui les jeutaille pas bill Luc jean écumait il taille Lacis just -Zufälligurl zu
peut élus silly mais les mes ishaute quils le aurais sans Les établis qui
des Louis de belle accueillis sell puss père peut olds sects it's allétells peutall asplait suite
Il -12 ) pas cause subit lequel euros le en as détaillé de till
PILONI balo -2
ispeulit Mais anglais appareils guilt gens ils en anglais glory pile le vous près
... still que y pais vida Los play quétejón Less via Leal su abuelos lástimaall) isa las
des audit elleguilt disons s'il souhait sous sirs vous lucius atoutes à pouvait lets pas
il taille glacis Lieu daily qui les jeutaille pas bill Luc jean écumait il taille Lacis just-Zufälligurl zu
peut élus silly mais les mes ishaute quils le aurais sans Les établis qui
des Louis de belle accueillis sell puss père peut olds sects it's allétells peutall asplait suite
Il -12 ) pas cause subit lequel euros le en as détaillé de till
PILONI balo -2
ispeulit Mais anglais appareils guilt gens ils en anglais glory pile le vous près
... still que y pais vida Los play quétejón Less via Leal su abuelos lástimaall) isa las
des audit elleguilt disons s'il souhait sous sirs vous lucius atoutes à pouvait lets
3. Definitions...
Dewatering may be defined as separation of
water from soil. OR
Dewatering may also be defined as taking the
water out of the particular construction
problem/ site.
Permanent ground water control is the
permanent stoppage of flow of water within
the ground.
4. Difference...
Construction dewatering
• It is separation or taking out
water from a particular
construction site.
• Purpose of dewatering is to
control sub - surface
hydrologic movement in
such a way so as to permit
construction activities in dry
environment.
Permanent ground water control
• It is permanent stoppage of
flow of water within the
ground.
• Purpose of permanent
ground water control is to
prevent entry of water in
underground constructions
during and even after
construction activities are
over.
5. Difference...
Construction dewatering
• It involves temporary
lowering of ground water
table at the construction
site to permit sub - surface
constructions.
• It is required only at the
time of construction.
• It is a dynamic process.
• Eg. During construction of
foundations, lift pits etc.
Permanent groundwater control
• It blocks the flow of ground
water, without interfering
with ground water table.
• It is required during and
even after construction.
• It is a static process.
• Eg. Areas of mining,
tunnels, basement, subways
etc.
6. Groundwater Control…
• Control of ground water always referred to
temporary and permanent exclusion.
• Temporary exclusion: lowering of the
water table and within the economic
depth range of 1500mm using subsoil
drainage methods, for deeper treatment a
pump or pumps are usually used.
• Permanent exclusion: the insertion of an
impermeable barrier to stop the flow of
water within the ground.
9. Groundwater Control…
• Problems of water in the subsoil:
• A high water table could cause flooding
during wet period.
• Subsoil water can cause problems during
excavation works by its natural tendency to
flow into the voids created by the excavation
activities.
• It can cause an unacceptable humidity level
around finished building and structures.
12. Sump and Sump pumping…
ADVANTAGES-
• Simple and cheap method of dewatering.
DISADVANTAGES-
• The sump takes up space within the
excavation.
• Can lead to water pollution problems silt-
laden water.
13. Construction Dewatering…
Shallow Wells
• These are suitable
for sandy gravels
and water-bearing
rocks for depth not
in excess of 5
meters and
principle upon
which they operate
is similar to that of
well point system.
14. Shallow Wells
ADVANTAGES
• It is used to extract large quantities of water
from a single hole.
DISADVANTAGES
• The limiting depth to which this method is
employed is about 8 m.
15. Construction Dewatering…
Well point system.
• A line or ring of small
diameter shallow wells
(called well points)
installed at close
spacing (1 to 3 m
centres) around the
excavation.
• Commonly used for
dewatering of pipeline
trenches.
16. Well point system
ADVANTAGES-
• Can be very flexible and effective method of
dewatering in sands or sands and gravel.
DISADVANTAGES-
• Drawdown limited to 5 to 6 m below level of
pump due to suction lift limits.
17. Construction Dewatering…
Deep wells system
• Wells are drilled at wide
spacing (10 to 60 m
between wells) to form
a ring around the
outside of the
excavation
• An electric submersible
pump is installed in
each well.
18. Deep wells system
ADVANTAGES
• Effective in a wide range of ground conditions,
sands, gravels, fissured rocks.
DISADVANTAGES-
• Drawdown limited only by wells depth and
soil stratification.
22. Permanent groundwater Control…
Ground Freezing
• Principle: To change the water in the soil
into a solid wall of ice.
• Seepage into a excavation or shaft can be
prevented by freezing the surrounding
soil. However, freezing is expensive and
requires expert design, installation, and
operation.
23. Permanent groundwater Control…
Ground Freezing Techniques
• Suitable for all types of saturated soils and
rock and for soils with a moisture content in
excess of 8% of the voids.
• The basic principle is to insert into the
ground a series of freezing tubes to form an
ice wall thus creating an impermeable
barrier.
• Takes time to develop and the initial costs
are high.
24. Permanent groundwater Control…
Ground Freezing Techniques
• The freezing tubes can be installed vertically for
conventional excavations and horizontally for
tunneling works.
• Normally using magnesium chloride and calcium
chloride with a temperature of -15 to -25 degree
Celsius which takes 10 to 17 days to form an ice
wall 1m thick.
• Liquid nitrogen could be used as the freezing
medium to reduce the initial freezing period if
the extra cost can be justified.
25. Ground freezing
ADVANTAGES
• Ground freezing is an extremely versatile
method for temporary ground improvement
or cutoff.
• It is applicable to the entire range of soils,
provided that the soil is near saturation or
completely saturated.
• It is also applicable to difficult ground
conditions including large boulders and
cobbles, or debris-rich non-engineered fills.
26. Ground freezing
DISADVANTAGES
• Ground freezing is a highly energy intensive
process, requiring refrigeration of massive
quantities of soil over extended periods of
time, which is very expensive.
27. Ground freezing
DISADVANTAGES
• Ground freezing requires plenty of monitoring:
brine temperatures, soil temperatures,
deflections of adjacent or nearby structures,
heaving and settlement at the ground surface,
groundwater salinity, pressures within freeze
pipes (leak detection), frozen wall thickness, and
the location and dimensions of possible windows
within the frozen wall, among other site specific
measurements.
28. Permanent groundwater Control…
Slurry trench walls
• These are used to contain
or divert contaminated
groundwater from drinking
water intake, divert
uncontaminated
groundwater flow from
contaminated sites and or
provide a barrier for the
groundwater treatment
system
Slurry trench cutoff walls
Soil-bentonite
Cement –bentonite
Soil-cement bentonite
29. Slurry trench wall
ADVANTAGES
• This is the only method that permits the visual
inspection of key material.
• Depth up to 200ft can be reached.
DISADVANTAGES
• Large excavation site, excavated soil storage,
slurry mixing, material storage etc.
• It is hard to ensure integrity of the wall.
30. Permanent groundwater Control…
Cutoff wall
• Vertical barriers or “cutoff walls” are often
used in geo-environmental engineering to
control the spread of contaminants.
• Cutoff curtains can be used to stop or
minimize seepage into an excavation where
the cutoff can be installed down to an
impervious formation.
32. Permanent groundwater Control…
Steel sheet piling
• Steel sheet piles are long structural sections with
a vertical interlocking system that creates a
continuous wall. The walls are most often used to
retain either soil or water.
33. Steel sheet piling
ADVANTAGES
• It is extremely light weight and makes it easier
to lift and handle.
• Steel sheeting is reusable and recyclable.
• The pile length is easily adaptable and can be
welded or bolted to make it work
34. Steel sheet piling
DISADVANTAGES
• It is extremely difficult to install steel sheeting
in soil that is rocky or has large boulders.
• Driving the sheets may cause neighborhood
disturbance.
35. Permanent groundwater Control…
Grouted barrier walls
• It consists of injecting a fluid material at a
certain pressure into soil or rock in order to
decrease the permeability and strengthen the
formation.
• Grout walls are typically formed by overlapping
grout columns which form a single row.
36. Grouted barrier walls
ADVANTAGES
• Depths greater than 200 ft can be achieved.
• Little waste material is generated.
DIS-ADVANTAGES
• This configuration involves more cost.
• Relatively high hydraulic conductivity values
are obtained.
37. Permanent groundwater Control…
Thin Grouted Membranes
• Work as permanent curtain or cut-off non
structural walls or barriers inserted in the
ground to enclose the proposed excavation
area.
• Suitable for silts and sands and can be
installed rapidly but they must be adequately
supported by earth on both sides.
• The only limitation is the depth to which the
formers can be driven and extracted.
39. Permanent groundwater Control…
Contiguous Piling
• Forms a permanent structural wall of
interlocking bored piles.
• Alternate piles are bored and cast by
traditional methods after which the
interlocking piles are bored using a special
auger or cutter.
• To ensure a complete interlock of all piles over
the entire length may be difficult therefore
the exposed face of the piles is usually
covered with a mesh or similar fabric and face
with rendering or sprayed concrete.
40. Permanent groundwater Control…
Contiguous Piling
• Suitable for most types of subsoil and has the
main advantages of being economical on
small and confined sites; capable of being
formed close to existing foundations and can
be installed with the minimum of vibration
and noise.
• Suitable for structures such as basements,
road underpasses and underground car parks.
42. Permanent groundwater Control…
Diaphragm Wall
• Are structural concrete walls which can be
cast in-situ or using pre-cast concrete
methods.
• Suitable for most subsoil and their
installation generates only a small amount of
vibration and noise.
• The high cost of these walls makes them
uneconomic unless they can be incorporated
into the finished structure.
• Normally use for basements, underground
carparks and similar structures.
44. Permanent groundwater Control…
Pre-cast Concrete Diaphragm Wall
• Have some applications with in-situ concrete
diaphragm walls.
• Lack in design flexibility.
• The panel or post panel units are installed in a
trench filled with a special mixture of bentonite
and cement with a retarder to control the setting
time.
• This mixtures ensures that the joints between
the wall components are effectively sealed.
• To provide stability, the panels of posts are tied
to the retained earth with ground anchors.
46. Permanent groundwater Control…
Grouting Methods
• Are used to form a curtain or cut-off wall in
high permeability soils where pumping
methods could be uneconomic.
• The curtain walls formed by grouting
methods are non-structural therefore
adequate earth support will be required and
in some cases this will be a distance of at
least 4m from the face of proposed
excavation.
47. Permanent groundwater Control…
Grouting Methods
• Grout mixtures are injected into the soil by
pumping the grout at high pressure through
special injection pipes inserted in the ground.
• The pattern and spacing of the injection pipes
will depend on the grout type and soil
conditions.
• Grout types:
• Cement grouts
• Chemical grouts
• Resin grouts
50. Equivalent Radius and Influence Range
Equivalent radius of excavation
r= √800ft * 500ft/√ = 357ft 112.5m
Height of water level in well
h = 160 – 70 – 5 = 85ft 25.5m
Influence range
R=C’(H-hw)√k =3000*(140-85)*0.3*√9.2*10^-5
=2200ft 670m
C= 3000 for wells
52. Rate of flow in wells
Multiple wells
For circular arrangement of wells
Q = 3.14k(H^2-h^2) / ln R – ln r
=3.14 * 0.00181*(140^2 – 85^2) /
ln 2200 - ln 357
= 38.7 cubic ft /min = 290gal / min
= 290/8 = 36.3 gal/min per well
53. Multiple Wells
Deep wel l size:
4” dia. for 36.3 gal/min
Header pipe:
4” dia. for 5*36.6 gal/min=181 gal/min
Discharge pump:
4” dia. Pump for 290 gal/min