New TVA Buildings

1 of 3
Image of New Temple View Apartment #1
Rendering of the New Temple View Apartment
2 of 3
TVA housing Building.PNG
3 of 3
TVA housing building2.PNG
Rendering for the New TVA Building
Planning, Design & Construction Department
1
of
3
About This Project
Additional Temple View Apartments are under construction. Temple View Apartment Buildings A3 and B3 are another two of the three structures for the second phase of the New Temple View Apartment Project. These two buildings have the same structure as in the new TVA Building A1, with a little difference in the exterior. Like the new TVA Building A1, TVA A3 and B3 will be constructed with insulated concrete forms (ICF) that have no wood to overcome many of the challenges of the existing construction. They are hurricane-resistant, mold-resistant, and insect-resistant and have high insulation value. Each unit will have the following:
- 9’-0” ceilings.
- Windows are located to increase airflow inside the unit to improve passive cooling.
- High-efficiency hot water system.
- Each unit has individual WIFI.
- Each unit has its own washer and dryer.
- New LED light fixtures.
- New hardwood cabinets.
- New quartz countertops.
- New luxury vinyl Tile flooring.
- New high-efficiency appliances.
- New furnishings.

1 of 4
TVA Phase 2 Overview-Feb 2025.jpg
TVA Phase 2–February 2025
Planning, Design & Construction Department

2 of 4
A4-Feb 2025.jpg
A4 Building–February 2025
Planning, Design & Construction Department

3 of 4
Feb 2025-A4.jpg
A4–February 2025
Planning, Design & Construction Department

4 of 4
A5-Feb 2025.jpg
A5 Building–February 2025
Planning, Design & Construction Department
1
of
4
Timeline and Updates of the Project
Completion Date
TVA A3-April 2024
TVA B3-August 2024
TVA B4-September 2024
TVA A4-February 2026
Recent Updates
February 2025
TVA Phase 2
- A4:
- Exterior painting completed.
- Trim completed.
- Roofing completed.
- Interior fixture installation continues.
- The final phase of cabinets is to be installed by the end of February.
- A5:
- Foundations have been completed.
- Structural columns have been put in place.
- The second-level floor joist installation on the east side has begun.
Phase 3 Preparation:
The road near the site has been closed, and preparations are underway to adjust the fence line to secure the area for construction. The demolition of Building H is expected to start at the beginning of March.
Construction Gallery
1 of 52
TVA Phase 2.PNG
January 6, 2023- (TVA Phase 2 Project Construction Site)
Planning, Design & Construction
2 of 52
TVA 11.11 Phase 2.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction Department
3 of 52
TVA 11.11 Phase 2.2 B3 Bldg Pad.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction
4 of 52
TVA 11.11 Phase 2.3 A3 Under Mat Slab utilities.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction
5 of 52
TVA 11.12 Phase 2.1.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction Department
6 of 52
Demolition of TVA BLDG. G.PNG
January 6, 2023-Building G Demolition Construction Site
Planning, Design & Construction
7 of 52
A3 TVA.PNG
January 6, 2023- A3 Building Pad
Planning, Design & Construction
8 of 52
Mat Slab-Concrete-TVA B3.PNG
January 6, 2023- Building B3 Foot Plan
Planning, Design & Construction
9 of 52
February 3, 2023- B3 and B4.PNG
January 27, 2023- Building A3
Planning, Design & Construction Department
10 of 52
A3-February 3, 2023.PNG
January 27, 2023-Building B4
Planning, Design & Construction Department
11 of 52
Feb 15- TVA PHASE 2.PNG
February 15, 2023- TVA Phase 2 Project Side View
Planning, Design & Construction Department
12 of 52
Feb 15-TVA B4.PNG
February 15, 2023- (TVA B4 Update)
Planning, Design & Construction Department
13 of 52
Feb 15-B3.PNG
February 15, 2023- (TVA B3 Update)
Planning, Design & Construction Department
14 of 52
Feb 15-TVA A3.PNG
February 15, 2023- (TVA A3 Update)
Planning, Design & Construction Department
15 of 52
TVA A3-March 14, 2023.PNG
March 7, 2023-Building A3
Planning, Design & Construction

16 of 52
B4.png
March 7, 2023- Building B3 & B4
Planning, Design & Construction

17 of 52
B4-May 2023.png
May 2, 2023- B4 Building Mat Slab on Grade
Planning, Design & Construction

18 of 52
May 2, 2023-A3 Back Exterior.png
May 2, 2023- A3 Building Back Exterior
Planning, Design & Construction

19 of 52
Building B4.2023.05.30.png
May 30, 2023- Progress Photo of Building B4
Planning, Design & Construction

20 of 52
Building B3 2023.05.30.png
May 30, 2023- Installation of insulated concrete form walls for building B3
Planning, Design & Construction

21 of 52
Building A3-2023.05.30.png
May 30, 2023 – Elevator shaft completed
Planning, Design & Construction

22 of 52
A3 back side 6-30-23.png
June 30, 2023 – A3 Back Side Completion
Planning, Design & Construction Department

23 of 52
TVA A3 June 30, 2023.png
June 30-2023 – A3 front windows and door installation
Planning, Design & Construction Updates

24 of 52
TVA Phase 2 June 30, 2023.png
June 30, 2023 – TVA Phase 2 Construction site
Planning, Design & Construction Department

25 of 52
Sept 15, 2023-B3.png
September 5, 2023- TVA Phase 2 Building B3 Construction
Planning, Design & Construction

26 of 52
A3. 2023.09.15.png
September 15, 2023 - TVA Phase 2 Building A3 construction
Planning, Design & Construction

27 of 52
B4-Sep 15, 2023.png
September 15, 2023 - TVA Phase 2 Building B4 Construction
Planning, Design & Construction

28 of 52
Sept 15, 2023-A3.png
September 5, 2023 - TVA A3 (Dining Area)
Planning, Design & Construction

29 of 52
A3-Sept 15, 2023.png
September 15, 2023- Dining Area/TVA A3
Planning, Design & Construction

30 of 52
Sept 15, 2023-B3.png
September 5, 2023- TVA Phase 2 Building B3 Construction
Planning, Design & Construction

31 of 52
A3. 2023.09.15.png
September 15, 2023 - TVA Phase 2 Building A3 construction
Planning, Design & Construction

32 of 52
B4-Sep 15, 2023.png
September 15, 2023 - TVA Phase 2 Building B4 Construction
Planning, Design & Construction

33 of 52
Building B4-12.08.2023.png
December 29, 2023-Construction Progress:Building B4 Facade
Planning, Design & Construction

34 of 52
Building A3-12.08.2023.png
December 8, 2023-Building A3 Construction Completion
Planning, Design & Construction

35 of 52
Building B3-12.08.2023.png
December 8, 2023 - Construction Progress Update of B3 Building
Planning, Design & Construction

36 of 52
2024-A3-March.png
April 26, 2024-Temple View Apartment A3 Completion
Planning, Design & Construction Department

37 of 52
b3-April 24, 2026.png
April 26, 2024-TVA B3 – Final Touches and Preparations Underway
Planning, Design & Construction Department

38 of 52
B4-April 26, 2024.png
April 26, 2024- B4 Building Exterior Nearing Completion
Planning, Design & Construction Department
39 of 52
TVA Building A4.JPG
May 20, 2024- Progressing Construction of ICF Walls on the First Floor, Steel Framework for Second Level Underway
Planning, Design & Construction Department
40 of 52
TVA Building B4.JPG
May 20, 2024- Landscaping and Interior Development.
Planning, Design & Construction Department
41 of 52
TVA Building B3.JPG
May 20, 2024-TVA B3 Completion
Planning, Design & Construction Department

42 of 52
B3 & B4 backyard.png
May 15, 2024- TVA B4 & B3 Landscaping
Planning, Design & Construction Department

43 of 52
B4 2024.png
July 3, 2024–TVA B4 Housing Construction
Planning, Design & Construction Department

44 of 52
2024 TVA.png
July 3, 2024–New TVA Housing Project Phase 2 Construction
Planning, Design & Construction Department

45 of 52
A3-2024.png
July 3, 2024–Completed Construction TVA A3 Building
Planning, Design & Construction Department

46 of 52
Sep.13.2024-A4 (1).jpg
September 13, 2024- TVA A4

47 of 52
A4-Sep 2024.png
September 13, 2024–TVA A4

48 of 52
Dec. 2024-TVA Phase 2.jpg
December 2024–TVA Phase 2
Planning, Design & Construction Department

49 of 52
Dec. 2024-A4.jpg
December 2024–A4
Planning, Design & Construction Department

50 of 52
Dec. 2024-A4 Bedroom.jpg
December 2024–A4
Planning, Design & Construction Department
51 of 52
A4-Dec. 2024.JPG
December 2024–TVA A4
Planning, Design & Construction Department
52 of 52
A5-Dec 2024.JPG
December 2024–TVA A5
Planning, Design & Construction Department
1