/ 15 June 2023

R83-million and three years later, only one RDP house has been built in Durban project

Screenshot 2023-06-15 at 07.00.44
The Namibia Stop 8 Housing Project in Inanda, eThekwini, started in 2019, but to date only this RDP house has been completed. Photo by Tsoanelo Sefoloko

The Namibia Stop 8 Housing Project in Inanda, eThekwini, started in 2019, but to date only one RDP house has been completed.

Residents say the construction company was on site from 2019 to 2020, but stopped because of the Covid pandemic.

According to eThekwini Municipality spokesperson Lindiwe Khuzwayo, the development – located about 30km from Durban centre – comprises 500 serviced sites and 343 new housing units. She said R83-million had been spent so far.

The money had been spent on roadworks, stormwater, sewers, platforms and foundations, water reticulation, and some top structures.

At a council meeting on 31 May it was revealed that R43-million is needed to complete the project, according to the Democratic Alliance human settlements spokesperson and member of the provincial legislature, Marlaine Nair.

She says no more money should be allocated without “a comprehensive report that addresses the project’s progress, challenges, and any potential irregularities”.

When we visited the area last week we found one road tarred for less than 500 metres, and the other roads still gravel. The stormwater system was incomplete. Some sewer trenches have been dug. A total of 13 houses were at foundation level. One house was complete.

eThekwini Councillor Zamani Khuzwayo (DA), who also sits on the human settlements and infrastructure committee, said the project was 51% complete and the new finishing deadline was December 2024.

Khuzwayo blamed delays on bureaucracy and obtaining the necessary approvals, the relocation of families to temporary housing units, Covid, the 2021 July unrest, and the KZN floods.

Families who were relocated in November 2019 said they were told the project would take 18 months. Three and half years later, they are still sitting in transit camps.

Community leader Thami Ngidi said residents had been sceptical from the outset. He said out of 500 families, only 311 agreed to be moved.

“Unfortunately the officials managed to convince some of us. We ended up agreeing to be moved,” said Ngidi.

The informal settlement of Namibia Stop 8 was established in 1960. Residents, who refused to be relocated, live in homes made of reused bricks and corrugated iron. Some built pit toilets for themselves.

Several hundred families who refused to move will have to be relocated to finish the project.

Resident Buzani Mkhize said, “I told them that I want to be closer when they build my house so that immediately when they finish I move in. We know houses are being [illegally] sold in other areas.”

Buzani Mkhize refused to move as the transit camp was too far away.

Tsepo Magubane said when his parents were relocated, his backyard room was demolished.

“I refused to go live in a one-room house with my parents and siblings. Our house is in the first row. We were told it will be done within six months but that never happened.”

Conditions at the transit camp are poor. Each family has to share a single room and there is a lack of toilets. Residents have to carry five and 10-litre buckets to the toilets for flushing. Water is currently being delivered by truck. Residents we spoke to said the water truck could be absent for weeks.

Mayor Mxolisi Kaunda said the municipality is busy with the repairs to vandalised pumps and apologised for the water situation.

This story was first published by GroundUp.