Gantt Chart is the most commonly used chart in project management. The more general definition of the Gantt chart is that it helps to keep track of the activities against time. Anything plotted against time can be represented in the form of a Gantt chart. For example, a team manager has given different tasks to their team members. Now keeping track of every task manually is a very difficult process but this can be easily achieved by the Gantt charts. With the help of Excel functions and Charts, we can automate the Gantt chart and so the progress of a project. 

Number representation of Date in Excel 

Before learning the Gantt chart in excel, you need to know how to format date in Number format in excel. For example, 3/13/2022 is in the date format and when converted to Number the value will be 44633.00. The use of the Number representation of Date might not seem very useful now, but when we will create a Gantt chart then the use of it will be very clear. Following are the steps: 

Step 1: Given a Date in cell C4. We can see that the format of the cell is a date. 

Given-a-Date-in-cell-C4

Step 2: Go to Home Tab, and select the drop-down menu in the Numbers section. Select the Number data type. 

Select-the-Number-data-type

Step 3:  You can see the value of date 3/13/2022 in number is 44633.00. 

You-can-see-the-value-of-date-in-number

Creating an Automatic Gantt Chart in Excel

Creating an automatic Gantt chart using simple horizontal bar charts. For example, Rohan wants to keep track of the Geeks for Geeks courses he is studying. Given a data set of Geeks for Geeks courses, its start time, and the number of days required to complete a particular course. Create a Gantt chart for it. The chart would be an automatic Gantt chart which changes with a change in the value of Start-Date and Days to Complete

Days-to-Complete-GFG-courses

Step 1: Go to Insert Tab, and in the charts section, click on the bar chart. 

Click-on-the-bar-chart

Step 2: An empty chart is created. 

An-empty-chart-is-created

Step 3: Right Click inside the blank chart. A drop-down appears. Click on Format Chart Area

Click-on-Format-Chart-Area

Step 4: Select Data Source dialogue box appears now click on Add button.

Select-Data-Source

Step 5: An Edit Series dialogue box appears.

Edit-series-dialogue-box

Step 6: In the Series name column. Select cell C5

Select-cell-C5

Step 7: In the Series Values column. Select the range C6:C12. Click Ok. 

Select-the-range-C6:C12-then-click-Ok

Step 8: Start-Date got added. Again click on Add button to add Days to Complete.

Start-Date-got-added

Step 9: The Edit Series dialogue box appears. In the Series name column. Select cell D5.

Select-cell-D5

Step 10: In the Series Values column. Select the range D6:D12. Click Ok

Select-the-range-D6:D12-and-click-Ok

Step 11: Now click on Edit Button to add Geeks for Geeks Courses.

Add-Geeks-for-Geeks-Courses

Step 12: An Axis Labels dialogue box appears. Select the range B6:B12. Click Ok.

Select-the-range-B6:B12-and-click-Ok

Step 13: The Select Data Source dialogue box reappears. Click Ok.

Click-Ok

Step 14: A basic bar chart is created. Now we can figure out there are three problems to converting a bar chart to a Gantt chart. 

  1. The courses appear in reverse order. The Excel Course should be at the top and the Git and Github should be at the bottom.
  2. The Blue Bar Lines should not be there in the Gantt chart.
  3. The earliest date in the given data set is 15-Jan. So the graph should start from 15-Jan but it is starting from 10-Dec. So, you need to remove all the redundant dates.

Solving all the problems one-by-one. 

A-basic-bar-chart-is-created

Step 15: Right-click inside the Y-axis i.e. inside the courses section. A drop-down appears and clicks on Format Chart Area.  

Clicks-on-Format-Chart-Area

Step 16: A Format-Axis dialogue box appears. In the Text Options, check the box Categories in reverse order. Now, all the courses will be reversed. 

Check-the-box-Categories-in-reverse-order

Step 17: The Labels got reversed. 

The-Labels-got-reversed

Step 18: Right Click on the Blue bar charts. A drop-down appears. Click on Format Data Series. 

Right-Click-on-the-Blue-bar-chartsClick-on-Format-Data-Series

Step 19: Format Data Series dialogue box appears. Go to Fill and Line, inside the fill section. Click on No Fill. All the blue bars will disappear. 

Click-on-No-Fill

Step 20: The only work left is to remove the redundant dates from the chart.  

Remove-additional-dates

Step 21: The topic studied at the start of the article i.e. Number representation of Date in Excel will significantly help you to remove the additional dates in the Gantt chart. In the given data set, you can see that the earliest date is 15-Jan. Now, you need to know what is the numerical value for 15-Jan. The value for 15-Jan in excel is 44576.00. Remember this number. 

Add-number-format

Step 22: Now, inside the date section of the chart, right-click on it. Click on Format Axis

Click-on-Format-Axis

Step 23: Format Axis dialogue box appears. In the Text Options section, click on the minimum value. Replace 44540.00 with 44576.00

Replace-44540.00-with-44576.00.

Step 24: An automatic Gantt chart is created. This chart is a dynamic chart that could adjust itself with a change in values in the data set. 

Automatic-Gantt-chart-is-created



G

News
Improve
Discuss
Do you want to advertise with us?Click here to know more

R

Creating a Gantt Chart With Milestones Using a Stacked Bar Chart In Excel

article_img
One of the most common and effective methods of displaying activities (tasks or events) plotted against time is a Gantt chart, which is frequently used in project management. On the left side of the chart is a list of the activities, and at the top is a suitable time scale. A bar is used to symbolize each activity, and the location and length of the bar correspond to the activity's beginning, middle, and finish dates. The following elements are crucial to any effective Gantt chart: The task list, which can be divided into groups and subgroups, runs vertically along the left side of the Gantt chart to define project activity.Timeline: Displays months, weeks, days, and years horizontally across the top of the Gantt chart.Dateline: On a Gantt chart, a vertical line displays the current date.Bars: On the right side of the Gantt chart, horizontal markers indicate tasks and display status, length, and start and finish dates.Milestones: Yellow diamonds that identify significant occasions, dates, choices, and outputsDependencies are thin grey lines connecting activities that must occur in a specific order.The percentage of work that has been completed or the color of the bars can be used t
Read More

C

How to Make a Dynamic Gantt Chart in Excel?

article_img
The Gantt chart is named after Henry Gantt, an American mechanical engineer and management consultant who devised it in the 1910s. In Excel, a Gantt diagram displays projects or tasks as cascading horizontal bar charts. A Gantt chart depicts the project's breakdown structure by displaying start and completion dates as well as other linkages between project activities, allowing you to track tasks against their allocated time or preset milestones. A Gantt chart allows you to know at a glance which tasks are currently the greatest priority, as well as the expected completion date of the article. Steps to Create an Excel Gantt Chart Step 1: Create a table with columns for data such as articles, start date, and end date, as seen in the picture below. Step 2: Following that, we must build a date section by creating a timeline and inserting the date formula: =DATE (year,month,day) After that using the =D5+1 formula, we extend the timeline by one day till 10 Jan 2021. Step 3: Now we are going to apply Conditional formatting by using this logical formula: =IF(AND(D$5>=$B6, D$5<=$C6),"YES","NO") Explanation: It will return "YES" if the D5 (01-Jan-2021) falls between B6 (01-Jan-2
Read More

How to Create a Gantt Chart in Excel [Free Template]

article_img
A Gantt chart in Excel is an essential tool for organizing and visualizing project timelines and milestones. This guide will show you how to create a Gantt chart in Excel using simple steps and a free Excel Gantt chart template, making it accessible for both beginners and professionals. Whether planning a project for personal use or team collaboration, leveraging Excel project management tools allows you to create a clear project timeline in Excel for better tracking and management.Disclaimer: Always ensure you customize charts based on your project requirements for maximum efficiency and accuracy.How to Create a Gantt Chart in ExcelWhat is a Gantt Chart in ExcelA Gantt Chart in Excel is a bar chart that visually represents a project schedule. It displays start and finish dates for project elements, aiding project managers in tracking progress and managing tasks effectively.How to Create a Gantt chart in Excel from ScratchWhen it comes to creating a Gantt chart in Excel, you can either use a predesigned template or create your own from scratch. To manually make a Gantt chart in Excel, follow the steps given below for your reference,Step 1: Prepare your Data This table must contain
Read More

Create a Gantt Chart in Google Sheets : Step by Step Guide

article_img
Managing project timelines effectively is crucial, and Google Sheets offers a powerful tool: the Gantt chart. This visual project management tool helps you track tasks, timelines, and dependencies with ease. In this comprehensive guide, we'll walk you through creating a Gantt chart in Google Sheets, using templates, and customizing your chart for optimal project management.Create Gantt Chart in Google Sheets - Free Templates Table of ContentWhat is the Gantt Chart in Google SheetsHow to Make Gantt Chart in Google SheetsHow to Customize Your Gantt Chart in Google SheetsFree Gantt Chart Template for Google SheetsHow to Remove the Chart in Google SheetsHow to Use Google Sheets Gantt Charts with DependenciesWhy use Gantt Chart in Google Sheets?What is the Gantt Chart in Google SheetsA Gantt chart in Google Sheets displays project tasks as bars along a timeline. Each bar shows the start, duration, and end dates of tasks, providing a clear overview of project progress. Its strength lies in tracking completed tasks, pending work, key milestones, expected outcomes, deliverables, and stakeholder responsibilities.How to Make Gantt Chart in Google SheetsFollow these easy steps to create a Gan
Read More

How to Make a Gantt Chart in Google Docs: Step by Step Guide

article_img
Are you looking to enhance your project management skills and streamline your workflow? Creating Gantt charts in Google Docs is an excellent way to visualize project timelines, allocate resources effectively, and ensure everyone stays on track. Gantt charts are powerful tools that allow teams to see the big picture while managing individual tasks. In this article, we'll explore the step-by-step process of creating Gantt charts in Google Docs, including tips on using templates, collaborating with team members, and customizing your charts for maximum impact. Whether you're a project manager, a student, or simply someone eager to organize tasks visually, this comprehensive guide will provide you with the knowledge you need to get started. So, let’s dive in and discover how to create Gantt charts that can transform your project management approach!Make Gantt Chart in Google Docs Table of ContentWhat is a Gantt Chart and How to Use it in Google DocsDifferent Ways to Create a Gantt Chart in Google Docs How to Create a Gantt Chart in Google Docs Using Google Sheets How to Create a Gantt Chart Using the Stacked Bar ChartHow to Save Basic Gantt Chart as a Template in Google DocsWhat is a Ga
Read More

Radar Chart or Spider Chart in Excel

article_img
Radar Chart is a pictorial representation of multivariate data. Multivariate data analysis in statistics is nothing but dealing with more than one outcome or observations. Radar graphs can be of two dimensions, three dimensions, or more on the basis of the multiple comparable variables used. The variables are represented on the axis starting from the same points with equal intervals on the axes. The number of axes in a radar graph solely depends on the number of variables used. The Radar Chart has various other names like spider chart, web chart, spider web chart, cobweb chart, irregular polygon, star chart, Kiviat Diagram, etc. The data from the observations in the form of tables are plotted on each axis and by joining all these points in the axes a polygon type structure is formed. So, the number of polygons is dependent on the number of observations. In this article, we will see how to plot a Radar Chart in Microsoft Excel for a given data set using two examples. Example 1 : Consider the table shown below which consists of the data of two Geek students who enrolled in our various courses. Our mentors have rated them on the basis of the student's performance in the individual
Read More

How to Create Automatic Rolling Months in Excel?

article_img
Microsoft created the spreadsheet Excel for Windows, macOS, Android, and iOS. Excel offers calculation, computation, visualization tools, pivot tables, and VBA. You will find a lot of cells in a spreadsheet. The names of the rows and the columns are both written in alphabetical order. The row and column addresses of each cell can be used to pinpoint its precise location. The spreadsheet's first top-left cell is A1. One spreadsheet contains 16384 columns and 1048576 rows in total (A to XFD). Automatic Rolling Months in Excel There are several ways to set up a series of Automatic Rolling Months: Using the Excel Toolbar's Fill Option By using the Fill Option from the Excel Toolbar, you can create a series of dates with automatic rolling months. Step 1: Enter the first date of the series in a cell. For instance, in cell C6, enter September 23, 2022: Automatic Rolling Months in Excel Step 2: Select all of the cells where you want the series to be inserted. Cells C6 to C17 were selected here: Automatic Rolling Months in Excel Step 3: Then, in the Editing Section of the Excel Toolbar, select Home>Fill. Select an option from the drop-down menu: Automatic Rolling Months in Excel Step 4:
Read More

I

How to Refresh a Pivot Table in Excel (Manual & Automatic Methods)

article_img
Refreshing a Pivot Table in Excel ensures your data reflects the most current and accurate information, which is essential for real-time updates and reliable reporting. Whether you're managing dynamic datasets or creating detailed reports, learning how to refresh Pivot Table in Excel is key to maintaining data integrity. This guide explores various methods, including manual and automatic Pivot Table refresh, while also addressing troubleshooting tips to help you keep your data updated and relevant.Table of ContentWhy Refreshing a Pivot Table Is ImportantHow to Refresh a Pivot Table in Excel Manually (Quick Way)How to Refresh All Pivot Tables at Once in a Excel WorkbookHow to Automate Pivot Table Refresh in Excel (2 Methods)Troubleshooting Pivot Table Refresh IssuesTips for Efficient Refreshing Pivot TableWhy Refreshing a Pivot Table Is ImportantRefreshing a Pivot Table ensures that it reflects the latest changes in your data. Without refreshing, the Pivot Table will display outdated information, leading to errors in analysis and decision-making.What Happens If Pivot Tables Are Not RefreshedOutdated Data: The Pivot Table won’t include new or modified data from the source.Inaccurate
Read More

How to Build an Org Chart in PowerPoint: Complete Guide

article_img
Create an Org chart in PowerPoint: Quick StepsOpen Power Point and Select SlideGo to the Insert Tab >> Click SmartArtChoose a Hierarchy Layout >> Add Details Adjust Layout >> Save and PresentAn organogram (also known as an organizational chart or org chart) is a visual representation of the hierarchical structure of an organization. It displays relationships and relative ranks of positions within the organization. Creating an organogram is essential for business presentations, employee handbooks, company proposals, or even internal meetings to provide clarity about roles and responsibilities.In this article, we will walk you through a step-by-step guide on how to create an organogram in PowerPoint using the tools and features PowerPoint offers, ensuring your chart is both visually appealing and easy to understand.How to Create an Organogram in PowerPointWhat is an Organogram and Why is it ImportantAn organogram is a graphical representation of a company's internal structure. It is used to display the hierarchical relationships between different roles, departments, or individuals within an organization.Key benefits of an organogram include:Clear Representation: Sho
Read More

I

WhatsApp's Latest Updates: Automatic Account Reports and Passkey Security Feature

WhatsApp plans to enhance security by introducing a passkey feature for iPhone users, streamlining login with biometric or facial recognition. To enhance user experience, WhatsApp has introduced two groundbreaking features for its users. The first is, the automatic account reports feature. This feature provides an easy way for you to stay updated about your account and channel activities automatically. and the second is a passkey feature for iPhone users, which will improve security and simplify other processes. Automatic Account ReportsThis new feature being introduced by WhatsApp will help users eliminate the process of manually requesting updates. This feature, once activated, will automatically generate reports for you. This feature will not only save you time but will also keep you informed about the changes in your account information. Passkey Feature for iPhone UsersWhatsApp is also rolling out a new feature only for iPhone users, focusing on security and convenience. The passkey feature allows you to use Face ID, Touch ID, or device passcode options to easily access your account without the need for passwords or OTPs. This feature takes you towards a more secure login proce
Read More
three90RightbarBannerImg