Vegas Sphere powered by 150 Nvidia RTX A6000 GPUs
July 15, 2024
Abdul-Rahman Oladimeji
Las Vegas
The Core Campus in Las Vegas, Nevada currently encompasses nine separate data centers with up to approximately 2.0 million GSF of space and up to 275 MW of 100% renewable power available to these facilities. We have one additional data center under construction at The Core Campus, which we expect will be operational in 2018 and that will provide approximately 340,000 GSF of additional space and have up to 40 MW of 100% renewable power available to the facility.
Switch powers the campus through the Switch Solar project is located in Clark County, Nevada northeast of Las Vegas on approximately 1,600 acres of land managed by the US Bureau of Land Management (BLM) in the Dry Lake Solar Energy Zone (SEZ).
There are two solar generation projects, Switch Station 1 and Switch Station 2 which produce 179-megawatts of power. The plants were originally part of a joint project between First Solar and NV Energy. In June 2017, EDF Renewable Energy acquired the two solar projects from First Solar.
• 250 MVA Switch owned substation
• 146 MVA of generator capacity
• 84 MVA of UPS S+S supply
• 44,000 tons of S+S cooling
• 5,400,000 cubic feet per minute
• 30 modular cooling towers
• 100% heat aisle containment
• t-scif™ designed for 1,500 watts
• 7,000+ cabinets / 350 t-scifs™
Launched in April 2013
Launched in 2016
Opened in 2017, the site uses a MOD 250 (Modularly Optimized Design). The site adds nearly 350,000 square feet and up to 40 megawatts (MW) of power
Cyxtera has an agreement to sell space in the SuperNap and is located in LV8. Century Link PR
Distance | Site | About |
---|---|---|
0.06 miles | CoreWeave: US West LAS1 | |
0.06 miles | Contegix Las Vegas | |
0.06 miles | Switch Las Vegas 7 | |
0.12 miles | Switch Edge 1 | |
0.16 miles | Switch Las Vegas 12 | |
0.23 miles | Switch Las Vegas 8 | |
0.34 miles | Switch Las Vegas 11 | |
0.42 miles | Switch Las Vegas 10 | |
0.44 miles | Switch Las Vegas 9 | |
0.68 miles | Switch: Las Vegas 15 | |
3.67 miles | DataBank Las Vegas LAS1 |
The site was a former zColo (Zayo) facility before being acquired in 2020.
|
3.85 miles | ColoXchange Las Vegas | |
4.09 miles | Fiberhub - Las Vegas |
|
4.51 miles | EdgeConneX Las Vegas |
EdgeConnex has rights to adjacent space to accommodate expansion
|
6.98 miles | Lumen: Las Vegas 3 | |
7.17 miles | Verizon: 2240 Corporate Cir | |
7.42 miles | LV.Net DC2 | |
8.39 miles | Flexential Carson I & II |
|
8.64 miles | LV.Net DC1 |
|
8.68 miles | Edged Energy: Las Vegas LAS01 |
Edged Energy intends to construct a data center campus in Las Vegas, with operations expected to begin in Q1 2028.
|
9.43 miles | Switch Las Vegas 5 | |
9.48 miles | Lumen: Las Vegas 2 | |
9.60 miles | Switch Las Vegas 2 | |
11.20 miles | Google Henderson NV |
|
13.26 miles | Lumen: Las Vegas (1 Aerojet) | |
14.36 miles | Flexential Las Vegas (Lone Mountain) |
The Lone Mountain Data Center in North Las Vegas opened in 2013. Flexential's Lone Mountain site is former ViaWest.AwardedTier IV Design Certification by the Uptime Institute for the design documents3,000 tons redundant, fault-tolerant cooling capacity
|
17.15 miles | Novva Las Vegas |
Novva’s newest purpose-built data center is located at 6115 Nicco Way, Las Vegas.
|
Switch, the technology infrastructure corporation headquartered in Las Vegas, Nevada is built on the intelligent and sustainable growth of the internet. Switch founder and CEO Rob Roy has developed more than 500 issued and pending patent claims covering data center designs that have manifested into the company’s world-renowned data centers.
Switch has PRIME campuses located in Las Vegas and Tahoe Reno, Nevada; Grand Rapids, Michigan; and Atlanta, Georgia.
July 15, 2024
Abdul-Rahman Oladimeji
Las Vegas
September 01, 2023
Abdul-Rahman Oladimeji
Switch
January 02, 2023
Switch
December 09, 2022
Abdul-Rahman Oladimeji
Switch
June 02, 2022
Abdul-Rahman Oladimeji
Switch