ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 1(I) BASIC IN<strong>FORM</strong>ATION<strong>FORM</strong> 1S. No. Item Detail1. Name of the projects/s Proposed Pellet Plant and CokeOven Plant along with CaptivePower Plant2. S. No. in the schedule 2(b) & 3(a)3. Proposed capacity/ area /length/tonnage/ to/behandled/ command area/ lease area/ number ofwells to be drilled Iron Ore Beneficiation Plant:1.5 MTPA Pellet Plant: 1.2 MTPA Producer Gas Plant:480 TPD or 75000Nm 3 /hour Coke Oven Plant: 0.225 MTPA Captive Power Plant:15 MW (WHRB based)Project Area – 78 AcresCapital Cost of the Project- Rs 420 Crores4. New/ Expansion/Modernization New5. Existing Capacity/ Area etc. NA6. Category of Projects i.e. ‘A’ or ‘B’ A7. Does it attract the general condition? If yes, Noplease specify.8. Does it attract the specific condition? If yes, Noplease specify.9. Location Latitude: 22˚21′36″NLongitude: 87˚18′1.8″EPlot/survey/Khasra No. Mouja: Nandar Chalk, J.L.No. 124VillageGokulpurTehsilKharagpur (Block)DistrictPaschim MedinipurState10. Nearest railway Station/airport along withdistance in kms.11. Nearest Town, city, District Headquaters alongwith distance in kms.12. Village Panchayats, Zilla Parishad, MunicipalCorporation, Local body (complete postal<strong>West</strong> <strong>Bengal</strong>Kharagpur Railway station – 3.4 kmfrom the project siteNetaji Subhash Chandra BoseInternational Airport, Kolkata:Around 121 km from the projectsite.Nearest town: Kharagpur Town - 3.5 km District Headquarter Midnapur -7.0 km4, Kalaikunda Gram Panchayat and7, Battala Gram PanchayatPage 1 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 1(II) ACTIVITY1. Construction, operation or decommissioning of the Project involving actions, whichwill cause physical changes in the locality (topography, land use, changes in waterbodies etc.)S. No. Information / Checklist confirmation Yes/No1.1 Permanent or temporary change in land use,land cover or topography including increasein intensity of land use (with respect to localland use plan)1.2 Clearance of existing land, vegetation andbuildings?Details thereof (withapproximate quantities /rates, wherever possible) withsource of information dataYes Land measuring 78 acres(partly agriculture and barrenland) will be acquired for theproject .The land is generallyflat and does not come underflood zone. Said plot of landwill be reformed / developedfrom its existing land use.YesThis project will be developedfollowing a land use plan,which will be made taking intoconsideration relevantguidelines / stipulations of theconcerned Authorities.Site clearing and preparationactivities will involve removalof scanty vegetation on theproposed plant site.1.3 Creation of new land uses? Yes Proposed project will bedeveloped following a plannedland-use plan. As far aspossible attempts will be madeto create minimum disturbanceto the existing land-use of theneighborhood. However, apositive change in the land usesdue to the proposed project isexpected.1.4Pre-construction investigations e.g. bore Nohouses, soil testing?-1.5 Construction works? Yes The civil works for theconstruction and developmentof the proposed project includebulk earthworks; constructionof factory sheds & utilities;internal roads & parking areas;drainage system; underground& overhead tanks etc.1.6 Demolition works? No -Page 3 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 11.7 Temporary sites used for construction worksor housing of construction workers?1.8 Above ground buildings, structures orearthworks including linear structures, cutand fill or excavationsUnderground works including mining or1.9Yes Suitable temporaryaccommodation for workerswill be made within the projectsite.Yes Please refer Pre-FeasibilityReport.tunneling?1.10 Reclamation works? No -1.11 Dredging? No -1.12 Offshore structures? No -1.13 Production and manufacturing processes? Yes Please refer Pre-FeasibilityReport.1.14 Facilities for storage of goods or materials? Yes All construction materials willbe handled through site storewithin the project boundary.1.15 Facilities for treatment or disposal of solidwaste or liquid effluents?NoYes-Iron ore tailings shall be storedin a pond, from where theoverflow shall be recycled inthe process. There will be nodischarge of any effluentoutside the plant boundary.Domestic wastewater will betreated in septic tank-soak pitsystem.Solid waste (dust as collectedin the dedusting systems) fromPellet Plant will be used in thepalletizing mix.Tailings from Beneficiationunit will be disposed off in adesignated location within theproject premises.1.16Facilities for long term housing ofoperational workers?1.17 New road, rail or sea traffic duringconstruction or operation?NoNoCoke breeze from Coke OvenPlant will be used in the pelletplant.Most of the workers employedshall be from theneighbourhood.The site is well connected tomain road way. No new road,rail or sea traffic duringconstruction or operation.Page 4 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 11.18 New road, rail, air waterborne or othertransport infrastructure including new oraltered routes and stations, ports, airportsetc?1.19 Closure or diversion of existing transportroutes or infrastructure leading to changes intraffic movements?1.20 New or diverted transmission lines orpipelines?1.21 Impoundment, damming, culverting,realignment or other changes to thehydrology of watercourses or aquifers?1.22 Stream crossings? No -1.23 Abstraction or transfers of water from Yesground or surface waters?1.24 Changes in water bodies or the land surfaceaffecting drainage or run-off?1.25 Transport of personnel or materials forconstruction, operation ordecommissioning?1.26 Long-term dismantling or decommissioningor restoration works?1.27 Ongoing activity during decommissioningwhich could have an impact on theenvironment?1.28 Influx of people to an area in eithertemporarily or permanently?NoNoNoNoNoYesNoNo----Daily water requirement of theproposed project will bearound 33 kl/hr, which will besourced from Kansabati River.-The plant location has properroad and rail linkages. Howrah-Mumbai Rail line is passingnear plant site and the nearestrailway station is Kharagpurwhich is 3.4 km from theproject site. Howrah-MumbaiNH-6 is passing close to theproject site. The nearest port isHaldia.Yes During construction 600persons will be employed for18 months, about 224 personswill get direct employmentduring the operation phase.1.29 Introduction of alien species? No -1.30 Loss of native species or genetic diversity? No -1.31 Any other actions? No ---Page 5 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 12. Use of Natural resources for construction or operation of the Project (such as land,water, materials or energy, especially any resources which are non-renewable or inshort supply):S. No. Information/checklist confirmation Yes/No2.1 Land especially undeveloped oragricultural land (ha)2.2 Water (expected source & competingusers) unit: KLD2.3 Minerals (MT) Yes2.4Construction material – stone, aggregates,sand / soil (expected source – MT)Details thereof (withapproximate quantities / rates,wherever possible) with sourceof information dataYes Land measuring 78 acres ispurchased from the private landowners for the proposed project.The land is generally flat anddoes not come under flood zone.It does not have any humansettlement.Yes Make up water requirement- 33 kl/hrYesSource - Kansabati River /BorewellIron ore fines: 1.5 MTPACoal: 0.266 MTPACoking coal : 0.3 MTPABentoniteLime Stone :: 0.0165 MTPA0.007 MTPAWill be procured mostly fromlocal sources.2.5 Forests and timber (source – MT) No -2.6 Energy including electricity and fuels(source, competing users) Unit: fuel (MT),energy (MW)YesTotal power requirement of theproposed Unit would be around 7MW, which will be sourced frominitially form WBSEDCL andafter commissioning of CPP frompropose 15 MW Captive PowerPlant.2.7Any other natural resources (useappropriate standard units)No -Page 6 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 13. Use, storage, transport, handling or production of substances or materials, which could beharmful to human health or the environment or raise concerns about actual orperceived risks to human health.S.No. Information/Checklist confirmation Yes/No3.13.2Use of substances or materials, which arehazardous (as per MSIHC rules) to humanhealth or the environment (flora, fauna,and water supplies)Changes in occurrence of disease or affectdisease vectors (e.g. insect or water bornediseases)Details thereof (withapproximate quantities / rates,wherever possible) with sourceof information dataNo -No -3.3Affect the welfare of people e.g. bychanging living conditions?No -3.4Vulnerable groups of people who could beaffected by the project e.g. hospital No -patients, children, the elderly etc.,3.5 Any other causes No -4. Production of solid wastes during construction or operation or decommissioning(MT/month)S.No. Information/Checklist confirmation Yes/NoDetails thereof (withapproximate quantities / rates,wherever possible) with sourceof information data4.1 Spoil, overburden or mine wastes No -4.2 Municipal waste (domestic and orcommercial wastes)4.3 Hazardous wastes (as per HazardousWaste Management Rules)4.4 Other industrial process wastes YesYes Solid waste of domestic /commercial origin that would begenerated in the Plant will bedisposed of suitably inconsultation with the concernedCivic body.No-Solid waste (dust as collected inthe dedusting systems) fromPellet Plant will be used in thepalletizing mix.Coke breeze from Coke OvenPlant will be used in the pelletplant.Page 7 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 14.5 Surplus product No4.6Sewage sludge or other sludge fromeffluent treatment4.7 Construction or demolition wastes Yes-Tailings from Beneficiation unitwill be disposed off in adesignated location within theproject premises.Will be utilized to develop theland.4.8 Redundant machinery or equipment No -4.9 Contaminated soils or other materials No -4.10 Agricultural wastes No -4.11 Other solid wastes No -5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)S.No. Information/Checklist confirmation Yes/No5.1Emissions from combustion of fossil fuelsfrom stationary or mobile sourcesYesDetails thereof (withapproximate quantities / rates,wherever possible) with sourceof information dataThe main air pollutant from theproposed project will beparticulate matter.5.2 Emissions from production processes Yes As stated above5.3Emissions from materials handlingincluding storage or transportYes5.4Emissions from construction activitiesincluding plant and equipmentYes Fugitive EmissionsDust or odours from handling of materials5.5 including construction materials, sewage Yesand wasteMain air pollutant will beparticulate matter.Water sprinkling system wouldbe used during the period of theprevention of fugitive dust5.6 Emissions from incineration of waste No N/AEmissions from burning of waste in openN/A5.7 air (e.g. slash materials, constructiondebris)No5.8 Emissions from any other sources No N/A6. Generation of Noise and Vibration, and Emissions of Light and Heat:S.No.Information/Checklist confirmation Yes/No Details thereof (withapproximate quantities/ rates,wherever possible) with sourceof information data with sourceof information data6.1 From operation of equipment e.g. engines,ventilation plant, crushersYesThe noise level below 75 dB(A)will be generated during operationof the proposed plant.6.2 From industrial or similar processes Yes From Fans, Pumps etc.Page 8 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 16.3 From construction or demolition Yes During construction, noise belowthe level of 75 dB(A) will begenerated.6.4 From blasting or piling Yes Noise level of the order of 75dB(A) will be generated duringpiling in the construction phase.6.5 From construction or operational traffic Yes Due to vehicular movement, therewill be slight increase in theambient noise level.6.6 From lighting or cooling systems No -6.7 From any other sources No -7. Risks of contamination of land or water from releases of pollutants into the ground orinto sewers, surface waters, groundwater, coastal waters or the sea:S. No. Information/Checklist confirmation Yes/No7.1From handling, storage, use or spillage ofhazardous materials7.2 From discharge of sewage or othereffluents to water or the land (expectedmode and place of discharge)7.3 By deposition of pollutants emitted to airinto the land or into waterDetails thereof (withapproximate quantities / rates,wherever possible) with sourceof information dataNo -NoYesIron ore tailings shall be stored ina pond, from where the overflowshall be recycled in the process.There will be no discharge of anyeffluent outside the plantboundary.Domestic wastewater will betreated in septic tank-soak pitsystem.Dust will be generated due todifferent project activities. Propercare will be taken to reduce dustemissions, wherever possible.7.4 From any other sources No -7.5Is there a risk of long term build up ofpollutants in the environment from thesesources?No -Page 9 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 18. Risk of accidents during construction or operation of the Project, which could affecthuman health or the environmentS.No. Information/Checklist confirmation Yes/No8.1From explosions, spillages, fires etc fromstorage, handling, use or production ofhazardous substancesYesDetails thereof (withapproximate quantities / rates,wherever possible) with sourceof information dataCompliance to Safety Rules andDisaster Management Plan wouldbe done.8.2 From any other causes No -8.3Could the project be affected by naturaldisasters causing environmental damage(e.g. Floods, earthquakes, landslides,cloudburst etc)?YesThe area falls under EarthquakeZone II as per Indian StandardSeismic Zoning Map.9. Factors which should be considered (such as consequential development) which could leadto environmental effects or the potential for cumulative impacts with other existing orplanned activities in the localityS. No. Information/Checklist confirmation Yes/No9.1 Lead to development of supporting utilities,ancillary development or developmentstimulated by the project which could haveimpact on the environment e.g.:• Supporting infrastructure (roads, powersupply, waste or waste water treatment, etc.)• housing development• extractive industries• supply industries• otherDetails thereof (withapproximate quantities / rates,wherever possible) with sourceof information dataYes The project will haveinsignificant impact on the roadnetwork around the projectsite.The project shall enhancethe socioeconomic status of thearea by increasing the demandfor housing, improving theemployment.9.2 Lead to after-use of the site, which couldhave an impact on the environment No -9.3 Set a precedent for later developments Yes As mentioned against Sl. No. 9.1.9.4 Have cumulative effects due to proximity toother existing or planned projects withsimilar effectsNo-Page 10 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 1(III) ENVIRONMENTAL SENSITIVITYS.No. Areas Name/Identity1 Areas protectedunder internationalconventions,national or locallegislation for theirecological,landscape, culturalor other relatedvalue2 Areas which areimportant orsensitive forecological reasons- Wetlands,watercourses orother water bodies,coastal zone,biospheres,mountains, forests3 Areas used byprotected,important orsensitive speciesof flora or faunafor breeding,nesting, foraging,resting, overwintering,migration4 Inland, coastal,marine orunderground waters5 State, Nationalboundaries6 Routes or facilitiesused by the publicfor access torecreation or othertourist, pilgrimareas7 DefenseinstallationsAerial distance (within 15 km.)Proposed project locationboundary- -River KansabatiAround 4.5kmNone -River KansabatiAround 4.5km- -None -Kalai Kunda Air Base9.2 kmPage 11 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 18 Densely populatedor built-up area9 Areas occupied bysensitive man-madeland uses(hospitals, schools,places of worship,communityfacilities)10 Areas containingimportant, highquality or scarceresources (groundwater resources,surface resources,forestry,agriculture,fisheries, tourism,minerals)11 Areas alreadysubjected topollution orenvironmentaldamage. (thosewhere existinglegalenvironmentalstandards areexceeded)12 Areas susceptible tonatural hazard whichcould cause theproject to presentenvironmentalproblems(earthquakes,subsidence,landslides, erosion,flooding or extremeor adverse climaticconditions)Kharagpur TownMidnapur TownAround 3.5 kmAround 7.0 km IIT Kharagpur Campus Around 5.0 kms. Talbagicha High School Around 5.2 kms. Hijli High School Around 5.5 kms. Dheesa Seema School Around 5.5 kms. Kharagpur Sub-division Hospital Around 3.4 kms. SE Railway Mixed HS School Around 3.1 kms. SE Railway Main Hospital Around 3.2 kms. DMS College Around 5.5 kms. Inda Girl’s School Around 4.1 kms. Kharagpur College Around 3.7 kms. Midnapur Medical College Around 7.0 kms. Mahananda School Around 7.0 kms. Midnapur Central Jail Around 9.0 kms. Vidyasagar University Around 7.8 kms. Gope Woman’s College Around 8.0 kms. Midnapur Mission Girl’s HS Around 8.7 kms.None -None -None -Page 12 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 1(IV) Proposed Terms of Reference for EIA studies:Scope of Work of EIAThe EIA shall cover the following:Description of the proposed project:The first task:” Description of the proposed project” forms a vital component of theEnvironmental Impact Assessment (EIA) as it provides the basis for evaluating thelikely causes of Environmental Impacts.Existing Environment and Baseline Conditions:The base line assessment will be carried out to identify potentially sensitive andcritical areas that may be affected by the project in an area of 10 km surrounding theproject location. The critical and sensitive targets shall be plotted on land use map ofproject impact area.The existing environment and baseline conditions will be established from:- Analysis of secondary/ published data.- Consultation with relevant statutory authorities, and Field visits forsupplementation of missing gaps.The key subject areas which the EIA shall address include Ecology and Natureconservation, Air quality, surface and water quality, soil quality, cultural heritage,landscape, land use, noise quality, etc in project impact area. Natural habitats likenational parks, wildlife reserves, sanctuaries, sacred grove, protected areas, forests,wetlands, major rivers and waterways if any, shall also be identified and marked.Assessment of Environmental Impacts:Based upon the results from the review of existing information, field visits, site datacollection and consultation, for each component of environment (physical, biologicaland socio economic) the positive, negative, direct and indirect, temporary andpermanent impacts will be evaluated along with an indication of the degree of impact,i.e., whether the impact is significant, moderate, minor or negligible. The degree ofimpact shall also be quantified by using state of the art air quality impact predictionmodels based on ISCST3 algorithms.Environment Management Plan and Mitigation Plan:For each significant negative impact identified, specialist shall work closely with theengineering team/technical consultants to suggest practicable measures to avoid ormitigate the impact. The mitigation of environmental impacts will be done by threemechanisms.Page 13 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 1 Introduction of mitigation features through the engineering practices. Implementation of environmental controls during construction and operation. Legislative control involving compliance with Indian environmental laws.The Environmental management plan shall include an estimate of capital andrecurring costs of mitigation measures and will identify the institutional frameworkfor implementation.Monitoring Plan:Having identified the significant environmental impacts that are likely to arise as aresult of the project, the project team shall specify what monitoring is required duringthe various phases of the project cycle.The monitoring plan will identify parameters and frequency of monitoring andresponsible organization.Page 14 of 15
ORISSA METALIKS PVT. LTD. <strong>FORM</strong> 1I do hereby give this undertaking that the data and information given in the applicationand enclosures are true to the best of my knowledge and belief and I am aware that if anypart of the data and information submitted is found to be false or misleading at any stage,the project will be rejected and clearance given, if any to the project will be revoked atour risk and cost.Date: 22 nd May, 2012Place: KOLKATAAnil Kr. MohtaDGM (Finance)Address:M/s Orissa Metaliks Pvt. Ltd.1, Grastin Place, Orbit House, 3 rd FloorKolkata-700 001Note:1. The projects involving clearance under Coastal Regulation Zone Notification, 1991shall submit with the application a C.R.Z map duly demarcated by one of theauthorized agencies, showing the project activities, w.r.t. C.R.Z. (at the stage of TOR)and the recommendations of the State Coastal Zone Management Authority (at thestage of EC). Simultaneous action shall also be taken to obtain the requisite clearanceunder the provisions of the C.R.Z. Notification, 1991 for the activities to be located inthe CRZ.2. The projects to be located within 10 km of the National Parks, Sanctuaries, BiosphereReserves, Migratory Corridors of Wild Animals, the project proponent shall submitthe map duly authenticated by Chief Wildlife Warden showing these features vis-à-visthe project location and the recommendations or comments of the Chief WildlifeWarden thereon (at the stage of EC).”3. All correspondence with the Ministry of Environment & Forests including submissionof application for TOR/ Environmental Clearance, subsequent clarifications, as maybe required from time to time, participation in the EAC Meeting on behalf of theproject proponent shall be made by the authorized signatory only. The authorizedsignatory should also submit a document in support of his claim of being anauthorized signatory for the specific project.”Page 15 of 15